Transportation


LAX – Tom Bradley International Terminal
All Area Plumbing prefabricated everything using GPS software to layout over 9,354 field points including 1,056 pipe spools, hot/chilled water, glycol and 43,646 linear-feet of pipe.
CPMCA Member:
All Area Plumbing, Inc.
Owner:
Los Angeles World Airports
Contractor:
Walsh Austin Joint Venture
Architect:
Fentress Architects
Project Location:
Los Angeles


LAX Bus Terminal
All Area Plumbing installed domestic hot/cold water,
condensate, waste & vent, storm drain, and natural gas
systems in this 44,260-square-foot, LEED Silver certified bus
terminal at LAX.
CPMCA Member:
All Area Plumbing, Inc.
Owner:
Los Angeles World Airports
Contractor:
Walsh Austin Joint Venture
Architect:
Anil Verma Associates, Inc.
Project Location:
Los Angeles


Amtrak Progressive Maintenance Facility
All Area Plumbing installed waste & vent, storm drain, compressed air, nitrogen, domestic cold/hot
water, industrial cold water, gas, vacuum piping systems, 95
prefabricated racks and 21,419 linear-feet of pipe.
CPMCA Member:
All Area Plumbing, Inc.
Owner:
National Railroad Passenger Corp.
Contractor:
Kemp Bros
Architect:
Kling Stubbins
Project Location:
Los Angeles


LAX – Central Utility Plant
Murray Company provided the detailing and 3-D BIM for the plumbing, HVAC/process and on-project systems
including water, oil, air, waste, vent, drains, equipment setting and erection.
CPMCA Member:
Murray Company Mechanical Contractors
Owner:
Los Angeles World Airports
Contractor:
Clark/McCarthy, A Joint Venture
Architect:
Gruen Associates
Project Location:
Los Angeles