El Centro Unit 3 Re-Powering Project, Epc
Back to case studies
The scope of work on this project included engineering, fabrication, civil/foundations, cooling tower erection, CTG and STG erection, HRSG’s (2), I&E, structural steel, piping, balance of plant equipment commissioning and performance testing.